title: "EV Charging Infrastructure New Buildings | AVANORTH"
canonical_url: "https://avanorth.ca/blog/electric-vehicle-charging-infrastructure-new-buildings"
last_updated: "2026-03-10T07:33:47.221Z"
locale: en
meta:
  description: "EV charging infrastructure guide for new buildings: charging levels, Ontario code requirements, load management, and future-proofing strategies."
  "og:description": "EV charging infrastructure guide for new buildings: charging levels, Ontario code requirements, load management, and future-proofing strategies."
  "og:title": "EV Charging Infrastructure New Buildings"
  "twitter:description": "EV charging infrastructure guide for new buildings: charging levels, Ontario code requirements, load management, and future-proofing strategies."
  "twitter:title": "EV Charging Infrastructure New Buildings"
---

AVANORTH Home

**Green Building**·May 5, 2026· 4 min read

# **Electric Vehicle Charging Infrastructure in New Buildings**

As electric vehicle adoption accelerates, new buildings must include EV charging infrastructure. Understanding charging levels, electrical capacity planning, and code requirements ensures future-ready construction.

**AVANORTH Team**

AVANORTH Construction

![Electric Vehicle Charging Infrastructure in New Buildings](https://avanorth.ca/_ipx/q_50&blur_3&s_10x10/uploads/blog/1773128027221-98b8e57c.webp)

Electric vehicle (EV) sales in Canada have grown from less than 3% of new vehicle sales in 2020 to over 10% in 2025, with the federal government mandating that 100% of new passenger vehicle sales be zero-emission by 2035. This rapid transition means that within a decade, the majority of vehicles parked at homes, offices, and commercial buildings will need electric charging capability. Buildings constructed today without EV charging infrastructure will require expensive retrofits.

---

## EV Charging Levels

| Level | Voltage / Amps | Power (kW) | Range Added per Hour | Typical Use |
| --- | --- | --- | --- | --- |
| Level 1 | 120V / 12A | 1.4 kW | 6-8 km | Standard household outlet (emergency / overnight top-up only) |
| Level 2 | 240V / 30-48A | 7.2-11.5 kW | 30-50 km | Home, workplace, commercial (the standard for building-integrated charging) |
| DC Fast Charging | 480V+ / varies | 50-350 kW | 250-1,000 km | Highway stations, fleet depots (not typical for buildings) |

> **For Building Design:** Level 2 charging at 240V is the standard for residential and commercial buildings. A Level 2 charger on a 40-amp circuit provides approximately 9.6 kW, enough to fully charge most EVs overnight (8-10 hours). Level 1 is too slow for practical daily use. DC fast charging is expensive and typically only installed at dedicated charging stations or fleet facilities.

---

## Code Requirements

### Ontario Building Code (OBC)

Recent amendments to the OBC require new buildings to provide EV charging infrastructure:

- **New residential (houses and townhomes):** A minimum 200-amp electrical panel with a dedicated 50-amp, 240V circuit roughed in to the garage or parking area for EV charging
- **New multi-unit residential:** At least 20% of parking spaces must be "EV-ready" (conduit and panel capacity in place), with the remaining spaces having a pathway for future conduit installation
- **New commercial/institutional:** At least 20% of parking spaces EV-ready

### Electrical Planning

| Building Type | Typical Per-Space Electrical Capacity | Panel Provision |
| --- | --- | --- |
| Single-family home | 40-50A, 240V circuit | Dedicated breaker space in main panel |
| Condo / apartment | 40A per space (or managed via load sharing) | Sub-panel in parking garage, metered per unit |
| Office building | 40A per space (Level 2) | Dedicated EV sub-panel with room for growth |
| Retail / hospitality | Varies (Level 2 or DC fast charge) | Utility-side transformer capacity for future load |

---

## Load Management

The biggest challenge for multi-unit buildings is that providing a dedicated 40-amp circuit for every parking space would require enormous electrical capacity. Load management solutions address this:

1. **Circuit sharing:** Two vehicles share one 40-amp circuit. The chargers communicate to alternate charging, reducing the peak load by 50%.
2. **Networked load management:** A central controller manages all chargers in the building, distributing available power across all connected vehicles based on priority, scheduling, or demand.
3. **Time-of-use optimization:** Chargers are programmed to charge during off-peak electricity hours (typically 7 PM to 7 AM), reducing both peak demand charges and energy costs.
4. **Demand response:** The building's energy management system can reduce or pause EV charging during peak building load events (e.g., hot summer afternoons when HVAC demand is highest).

---

## Installation Considerations

- **Conduit routing:** Plan conduit pathways from the electrical room to every parking space at design stage. Retrofitting conduit through finished parking structures is extremely expensive.
- **Ventilation:** Indoor parking with EV charging does not require additional ventilation beyond standard code requirements (EVs produce no exhaust). However, the small risk of thermal runaway in a lithium battery should be considered in fire protection design.
- **Metering:** In multi-unit residential buildings, individual sub-metering for each charger allows the cost of charging to be billed to the unit owner rather than the condominium corporation.
- **Future-proofing:** Even if only 20% of spaces are equipped initially, size the electrical infrastructure (transformer, switchgear, panel) for 100% of spaces to avoid costly future upgrades.

> **AVANORTH EV-Ready:** Every new building we construct includes EV charging infrastructure designed for 100% future coverage, not just the minimum code requirement. We route conduit to every parking space and size the electrical service for full build-out. Our residential clients receive a dedicated 50-amp EV circuit as standard. This forward-thinking approach adds minimal cost during construction but saves thousands in retrofit costs later.

#electric-vehicles #green-building #infrastructure

### **Share this article**

[Share on X (Twitter)](https://twitter.com/intent/tweet?text=Electric%20Vehicle%20Charging%20Infrastructure%20in%20New%20Buildings&url=https%3A%2F%2Favanorth.ca%2Fblog%2Felectric-vehicle-charging-infrastructure-new-buildings) [Share on LinkedIn](https://www.linkedin.com/sharing/share-offsite/?url=https%3A%2F%2Favanorth.ca%2Fblog%2Felectric-vehicle-charging-infrastructure-new-buildings) [Share on Facebook](https://www.facebook.com/sharer/sharer.php?u=https%3A%2F%2Favanorth.ca%2Fblog%2Felectric-vehicle-charging-infrastructure-new-buildings) [Share on WhatsApp](https://wa.me/?text=Electric%20Vehicle%20Charging%20Infrastructure%20in%20New%20Buildings%20https%3A%2F%2Favanorth.ca%2Fblog%2Felectric-vehicle-charging-infrastructure-new-buildings)

## **Related Articles**

- [![Building Resilience: Climate-Adapted Construction in Canada](https://avanorth.ca/_ipx/s_600x338/uploads/blog/1773128055243-cd164e0a.webp)**Green Building**<h3>**Building Resilience: Climate-Adapted Construction in Canada**</h3>

  Climate change is increasing the frequency and severity of extreme weather events in Canada. Climate-adapted construction designs buildings to withstand floods, wildfires, ice storms, extreme heat, and wind.4 min read](https://avanorth.ca/blog/building-resilience-climate-adapted-construction-canada)
- [![Embodied Carbon in Construction Materials: Measuring and Reducing](https://avanorth.ca/_ipx/s_600x338/uploads/blog/1773128054576-e593a519.webp)**Green Building**<h3>**Embodied Carbon in Construction Materials: Measuring and Reducing**</h3>

  Embodied carbon is the CO2 emitted during material extraction, manufacturing, transport, and construction. As buildings become more energy-efficient, embodied carbon becomes the dominant source of lifecycle emissions.3 min read](https://avanorth.ca/blog/embodied-carbon-construction-materials-measuring-reducing)
- [![Heat Pump Technology: Efficient Heating and Cooling](https://avanorth.ca/_ipx/s_600x338/uploads/blog/1773128053723-376f7f17.webp)**Green Building**<h3>**Heat Pump Technology: Efficient Heating and Cooling**</h3>

  Heat pumps move heat rather than generating it, delivering 2-4 times more energy than they consume. Modern cold-climate heat pumps now operate efficiently even at -25 degrees C, making them viable for Ontario.3 min read](https://avanorth.ca/blog/heat-pump-technology-efficient-heating-cooling)
- [![Low-Carbon Concrete: Reducing Cement's Carbon Footprint](https://avanorth.ca/_ipx/s_600x338/uploads/blog/1773128053062-9bd0d49c.webp)**Green Building**<h3>**Low-Carbon Concrete: Reducing Cement's Carbon Footprint**</h3>

  Cement production accounts for approximately 8% of global CO2 emissions. New low-carbon concrete technologies and supplementary cementitious materials are dramatically reducing the carbon footprint of the world's most-used building material.3 min read](https://avanorth.ca/blog/low-carbon-concrete-reducing-cement-footprint)

### **Have a project in mind?**

Let's discuss how AVANORTH can bring your construction project to life — on time and on budget.